HS-5K Residential Energy Storage Installation Guide

Documentation/Installation

HS-5K Residential Energy Storage Installation Guide

InstallationVersion V1.2Updated 2026-11-01

This guide covers installation and commissioning of the EVX HS-5K residential energy storage system.

Safety Instructions

  • Isolate the grid before installation and display warning signs.
  • Do not store battery modules above 85% humidity.
  • Wear insulated gloves and use insulated tools.
High voltage: battery stack voltage can reach 400V.

Before Installation

ItemRequirement
LocationVentilated, dry, away from direct sunlight
Temperature-10°C to 45°C
Wall load≥ 120kg

Installation Steps

  1. Fix and level the wall bracket.
  2. Mount the battery and inverter.
  3. Connect the ground cable.
  4. Connect PV, battery and load cables.
  5. Check terminal torque before power-on.

Troubleshooting

For E03, check the battery communication cable. E07 usually indicates abnormal grid voltage.