HS-20K Home Energy Management
家庭 EMS 的模式配置、备电策略与 App 使用。

Scope
This document is for EVX installation, commissioning, service and acceptance teams. Confirm the model, site conditions and local grid requirements before starting.
Procedure
- Check the nameplate, documents and site conditions.
- Complete wiring and verify earthing and protection.
- Power up and check communications, alarms and operating status.
- Record the checks and complete handover or acceptance.
Checklist
| Item | Requirement |
|---|---|
| Environment | Ventilated, dry, within datasheet range |
| Earthing | ≤4Ω, secure connection |
| Communications | EMS, meter and platform data healthy |
| Safety | Fire, E-stop and alarm interlocks active |
Notes
- Isolate and tag the equipment before work.
- High-voltage work must be performed by qualified personnel.
- Refer to the current datasheet for exact values.