X-20 Three-Phase Inverter Installation

Documentation/

X-20 Three-Phase Inverter Installation

X-20 的安装位置、通风、并网接线与保护配置。

X-20 Three-Phase Inverter Installation
X-20 Three-Phase Inverter Installation · Demo document

Scope

This document is for EVX installation, commissioning, service and acceptance teams. Confirm the model, site conditions and local grid requirements before starting.

Procedure

  1. Check the nameplate, documents and site conditions.
  2. Complete wiring and verify earthing and protection.
  3. Power up and check communications, alarms and operating status.
  4. Record the checks and complete handover or acceptance.

Checklist

ItemRequirement
EnvironmentVentilated, dry, within datasheet range
Earthing≤4Ω, secure connection
CommunicationsEMS, meter and platform data healthy
SafetyFire, E-stop and alarm interlocks active

Notes

  • Isolate and tag the equipment before work.
  • High-voltage work must be performed by qualified personnel.
  • Refer to the current datasheet for exact values.