C&I Storage Grid Connection Checklist
Align documents, protection and communications before grid connection to reduce site loops and acceptance delays.

Documents
- Datasheets, type-test reports and certificates
- Grid application, single-line diagram and protection settings
- Electrical test reports and earth-resistance records
Protection and communications
| Item | Check |
|---|---|
| Protection | Over/under voltage, over/under frequency, anti-islanding |
| Points list | Telemetry, status, control and meter direction |
| Fire interlock | Alarm, shutdown and ventilation linkage |
Acceptance
Run at low power for 30 minutes, verify power direction, meter readings and alarms, then ramp to rated power.